Weil McLain Boiler 550 141 951 1002 User Manual

Gas-fired  
water boiler  
Conversion Instructions  
Natural to Propane Gas  
STOP! Read this notice  
These instructions are only for propane conversion of a boiler that has already  
been installed. If you are converting a new boiler, not yet installed, do not use  
these instructions. Instead, read and follow all instructions in the Boiler Manual.  
Perform the propane conversion procedure on page 9 of the Boiler Manual  
only in the proper sequence.  
These instructions are for conversion of the following boilers from natural gas to propane  
gas. (The propane gas orifice is located in the Propane Conversion Kit envelope.)  
Boiler Model  
Orifice stamping  
Ultra-155 ................................. 155-LP  
Ultra-230 ................................. 230-LP  
Ultra boilers are shipped ready to fire natural gas ONLY. You must install the  
propane orifice if the boiler will be connected to propane. Follow all instructions  
in this document and the Boiler Manual. Failure to comply could result in severe  
personal injury, death or substantial property damage.  
This conversion must be installed by a qualified installer/service technician in  
accordance with the Weil-McLain instructions and all codes and requirements  
of the authority having jurisdiction. The qualified agency performing this work  
assumes responsibility for this conversion.  
Follow all instructions in proper order.  
Do not tamper with orifice size. DO NOT change or modify orifice in any way.  
Do not leave an uninstalled orifice in the building.  
Verify the following before proceeding:  
Propane gas operation requirements  
Pipe sizing for propane gas  
1. Contact propane gas supplier to size piping, tank and install a 100% lockup gas pressure  
regulator, or to verify size and condition of existing piping and equipment.  
Propane supply pressure requirements  
1. Adjust propane supply regulator provided by gas supplier for 13" w.c. maximum pressure.  
2. Pressure required at gas valve inlet pressure port:  
Maximum: 13" w.c. with no flow (lockup) or with boiler on.  
Minimum: 4" w.c. with gas flowing (verify during boiler start-up per Boiler Manual).  
3. After connecting propane gas line to boiler, and BEFORE operating, check gas pressure. If  
gas pressure is not in the range above, close manual gas valve and contact gas supplier to  
correct the problem before attempting to start or operate the boiler.  
Part number 550-141-951/1002  
 

Western Digital Computer Drive WDBPDZ0020BAL User Manual
Whirlpool Dishwasher W10254964 User Manual
Whirlpool Freezer ET22ZM User Manual
Whirlpool Oven AKZM 838 User Manual
Whirlpool Refrigerator 6ET18DK User Manual
Windsor Carpet Cleaner 86037880 User Manual
Xantech Satellite Radio 172 77 User Manual
Zanussi Washer Dryer WJD 1257 S User Manual
Zenoah Brush Cutter BC3401FW User Manual
Zephyr Ventilation Hood Z1C01ML User Manual